Net Revenue Projections tab
The Net Revenue Projections tab displays the planned labor contribution "net" of interference from non-labor items such as profit, expenses, and consultants. The report projects each project phase on a monthly basis over the next two years but can be summarized at multiple levels.
Note: You can change the name on this report based on individual company configuration.
To access this tab
On the Projections and Analysis window, click the Staffing Projections tab .
Data grid
The following fields are displayed in the data grid. All the fields are read-only.
Data can be grouped, filtered and sorted using the column headers. This allows project managers to quickly view the available information from different perspectives.
Field | Description |
---|---|
Active / Opportunity | Indicates whether the effort is an active project (regular, promotional or overhead) or an opportunity. |
Project Number | The project number |
Project Name | The project name |
Office | The office associated with the project phase |
Phase | The phase name |
Phase Starts | The start date for the phase from the Schedule tab. |
Phase Ends | The end date for the phase from the Schedule tab. |
Budget % | The percent of the overall project budget represented by the phase revenue. This value comes from the Labor Budget tab and is based on the proportion of planned labor to the overall budget. |
Team Complete |
This column displays the percent complete of the assignments from the Team tab for all assignments in the phase. When detailed staffing is assigned, Team Complete is calculated using the detailed work plan data, instead of assuming an even distribution of hours over the weeks of the assignment. For additional details, please refer to ETC Hours on the Team tab. |
Task Complete | This column displays the percent complete for all tasks for the phase. It is calculated based on the % Complete values entered by the project manager on the Tasks tab. The Tasks Complete value is a weighted average for task percentages identified on the Tasks tab based upon effort. |
Schedule Complete | This column displays the percent complete value for the phase from the Schedule tab. |
Phase Revenue | The projected net revenue for the phase. Calculated by multiplying the Project Net Revenue value by the Budget % value for the phase. |
Earned |
The amount of revenue earned to date for the phase. Earned revenue is calculated by multiplying the Task Complete value for the phase from the Billing tab by the fee for that phase. If no Task Complete value is available, earned revenue is calculated using the Team Complete value. If neither Task Complete or Team Complete is available, earned revenue is calculated using the Schedule Complete value. |
Remaining | The amount of planned net revenue remaining for the phase. Calculated as Phase Revenue less the Earned value. |
Monthly Columns |
Monthly columns display projected net revenue going forward two years. Project Analyzer uses the Billing End Cut-Off date to determine which month is the first month shown. For example, if the Billing End Cut-Off date is the 5th of the month, the September column will continue to appear until October 5th. The Billing End Cut-Off date is configured on the General Settings tab in System Configuration. |