Phase on Hold dialog box

Use this dialog to place a project phase on hold.

Selected Phase

The name of the phase selected in the Schedule tab.

Start Hold

The start date for the hold.

End Hold

The end date for the hold.

Duration in Business Days

The duration of the hold in business days. This number is calculated using the entered start and end hold dates.

Options

Probability

The probability of restarting the phase.

To access this dialog

From the Schedule tab, select the row for a phase, right click and select Phase Hold from the pop-up menu.