Load Labor Budget From Tasks
Perform the following steps to populate the Labor Budget tab with assignment data from the Tasks tab.
Prior to loading labor from the project tasks, use the Discipline column in the Tasks tab to associate a task with a discipline. This value is used for grouping tasks and when using the Load Labor from Tasks tool. This association is optional but highly recommended in order to enhance the value of the tasks list.
To load task data into the labor budget
If you do not select this checkbox, task effort data imported from the Tasks tab is added to any values currently existing on the Labor Budget tab.
Selecting Scale Effort to fit Available Labor Budget changes the imported task effort values to fit into the available labor budget.
Related topics
Load Labor from Tasks dialog box